Welcome to Elaine's Retirement Journal

I retired from John Muir Health as a Project Manager on May 22, 2011 after several attempts at doing so.
This blog is to experience my new Projects as Project Manager, Leisure.
I have several other blogs related to all the Morgan's Over America- see links.
As my Sister and I went together on the same trip to Provence this summer, and as she is a much better writer than I am, I have provided links to her writing where appropriate.



















Friday, October 28, 2011

ROOF TRUSSES ARRIVE TODAY

All the framing has been completed and the roof trusses arrived today.
 The driver arrived earlier than expected y from Oakdale, so we had to dash out quickly to take pictures.

Naturally the trusses weren't loaded on the truck in the order they needed to be laid on the framing.



 The driver was a very patient man, who moved and removed trusses to get them to their needed location. There are trusses for the lower garage and the upper garage, which required moving the very large truck to complete the task.





Also completed today was the stairway from the lower storage room to the upper storage room.

Next week the trusses will be set in place.

Monday, October 10, 2011

DAY 34- Gravel Laid Down

Just prior to the rain, the Greg laid the gravel down for both driveways and the parking pad. To the lower right is the lower garage floor, and the upper garage is above the framing. As of today, Monday Oct 10, two f the upper walls have been framed. Pictures tomorrow. 


Upper Driveway (will be asphalt eventually)
Parking pad
Plywood that will be laid over the upper garage floor before the concrete is poured

Monday, October 3, 2011

Day 30 or So-Lower concrete and Upper Framing

I am behind on postings due to preparations for our son's wedding this week. There will be no pictures for the next week, as framing is being done on the upper garage.
The lower garage had its 4 inch concrete floor poured this week. The 4 inches is so husband can have a "lift" to work on his cars. You can also see the framing for the floor of the upper garage.

The framing to support the upper garage is also completed. After plywood, concrete will be poured over this suspended floor.

The unexpected, expensive, retaining wall to keep the driveway and the people from falling from the upper driveway.
At the far right of the retaining wall will be a path down to the lower level stairs (another "work order") in order to allow access to this hill for landscaping purposes and to travel from the upper garage to the house if one doesn't want to go through the garage, through the man cave and out the lower stairs.
I asked husband, what is "this wall". He didn't tell me because it wasn't a "work order $$$". Apparently the concrete contractor kicked the wall at the right, and it collapsed and broke a piece off, probably because of an air pocket. So this new wall is a fix for the broken wall. Hmmm... I wonder how many other air pockets there are?

Until after the wedding....