With the back fill completed and lumber delivered, the carpenter guys started building the sub frame for the upper garage's concrete slab. There will be a 3 " concrete slab poured over the wood, somewhat suspended.
The concrete guys also started work on the lower garage slab, in preparation for pouring the the 4 " slab (to support a "lift") next week. The wing walls also will be built and hopefully poured next week as well. They are to hold in the dirt from slipping down the slope.
I headed back to the Bay Area home for final preparations for the big wedding in October.